XTX Switches On 22.5 MW Kajaani Data Center, Grid Permits Threaten Rest

XTX Markets opened a 22.5 MW data center in Kajaani, Finland — 9% of its 250 MW target. €400m spent of a €1bn plan; permits for power lines now take years.

XTX Markets Opens Finnish Data Center, Says Red Tape Puts Expansion at Risk
XTX Markets Opens Finnish Data Center, Says Red Tape Puts Expansion at Riskblickpixel / pixabay

Execution notes

  • XTX opened a 22.5-megawatt data center in Kajaani, Finland, on Tuesday, its first owned facility
  • Power is secured for only two of five planned buildings; the third, due mid-2028, lacks guaranteed supply
  • Construction spend exceeds €400 million, roughly 40% of the €1 billion earmarked in January 2025
  • Expropriation permits for power lines 'that once took months can now take years,' COO Mike Irwin said
  • A six-week migration moved 417 petabytes on 385 servers, roughly 26 metric tons of drives, off leased space

XTX Markets opened its first owned data center on Tuesday — a 22.5-megawatt facility in Kajaani, Finland — and warned in the same statement that permit delays for new power lines could put further investment at the site at risk.

The capacity figure matters more than the ribbon-cutting. When XTX unveiled the Kajaani plan in April 2024, it targeted 250 megawatts. The 22.5 MW now running equals 9% of that goal, by FinanceMagnates.com's calculation. Power and grid connections cover only the first two buildings on the 193-hectare campus. A third building, already under construction and due in mid-2028, has no guaranteed electricity supply.

What has XTX actually spent, and what is secured?

Construction has consumed more than €400 million (about $465 million), mostly paid to Finnish contractors, according to the firm. That is roughly 40% of the more than €1 billion XTX earmarked for the site in January 2025.

The constraint XTX names is not capital. Its three UK entities reported combined net revenue of £3.93 billion (about $5.3 billion) for 2025, up 43% year on year, with profit after tax of £1.71 billion. The firm, controlled by founder Alex Gerko, ran more than 25,000 GPUs for research in 2024, mostly from Nvidia, and its models price more than 53,000 instruments.

Where does the bottleneck sit?

Mike Irwin, chief operating officer at XTX Markets, singled out permits to expropriate land for the transmission lines that would feed the later buildings.

"Expropriation permits that once took months can now take years," Irwin said.

He said government bureaucracy and a lack of engagement were putting plans to invest billions more at risk. XTX would contribute financially to the infrastructure, he added, but without that engagement future investment decisions would be called into question. Note what the statement does not specify: which agencies, which projects, or what a firm funding grid build-out expects in return.

Finnish public broadcaster Yle reported that XTX plans five data centers along the Kajaani River and would build faster given enough power. On that count, three of the five buildings depend on electricity that is not yet secured. That is an asserted build plan, not a contracted one.

How did the migration off leased space go?

Kajaani exists to end XTX's reliance on rented computing. When the €1 billion figure emerged in January 2025, then-Chief Technology Officer Joshua Leahy said the firm's compute needs had outgrown leasing options. Leahy left XTX and its board in March 2026.

The storage move off leased space is complete. In one six-week window, XTX said, it shifted 417 petabytes on 385 servers — roughly 17,000 drives weighing 26 metric tons — from a rented data center five kilometers away. The second building is due to start operating in 2027.

Who works there, and what does the firm give back?

The site employs more than 30 full-time staff with room for 50. XTX pledged more than €1.6 million to Finnish education projects, including €520,000 for Kajaani University of Applied Sciences.

The open question for desks watching XTX's infrastructure spend: whether the mid-2028 third building slips if expropriation permits continue to run to years, and whether the remaining 227.5 megawatts of the original 250 MW target survive the grid queue at all.

via events.financemagnates.com (Original)

More from James Calloway

James Calloway

Show full bio

Correspondent covering technology and product news in market microstructure and institutional trading at Order Flow Brief.

91 articles

Blotter · related prints

  1. Deutsche Börse Opens 24/7 Trading for DAX 40 Equities

  2. smartTrade UK Unit Lifts Profit 22% to £3.39m on Flat Sales

  3. TP ICAP Q3 Revenue Up 11% to £620 Million as Broking Outpaces Liquidnet

  4. SGX FX Widens Aladdin Link as Buy-Side FX Volumes Hit $190.2 Billion

  5. Percent Launches PCTX, an Electronic Trading Venue for Private Credit

« Previous printNext print »